Skip to content Skip to sidebar Skip to footer

Connection of the shopping and entertainment center to 10 kV power grids (Kropyvnytskyi city, Ukraine)

Connection of the shopping and entertainment center to 10 kV power gridsAlteco company has connected a shopping and entertainment center in Kropyvnytskyi to the power grids of a local operator (distribution system operator). The connection was made at a voltage of 10 kV according to category II. To coordinate the actions of designers, engineers, lawyers, suppliers, contractors and specialists of the distribution system operator, Alteco company acted as a general contractor.

Alteco company has connected a shopping and entertainment center in Kropyvnytskyi to the power grids of a local operator (distribution system operator).

The connection was made at a voltage of 10 kV according to category II.

To coordinate the actions of designers, engineers, lawyers, suppliers, contractors and specialists of the distribution system operator, Alteco company acted as a general contractor.

Connection of the shopping and entertainment center to 10 kV power grids

A feature of this object was the cramped conditions on the territory of the Customer itself, as well as the density of other engineering networks and buildings in the central part of the city.

a modular-type CTSmodular-type CTS

Due to cramped conditions, a modular-type CTS was used

CTS_Kropyvnytskyi

As part of the general contract, our specialists performed the following works:

  1. Drawing up an application and obtaining technical conditions (TC).
  2. Collection of initial data for the start of design work, including the preparation of technical specifications for topographic survey.
  3. Development of design and estimate documentation for own 10/04 kV transformer substation at the “Working Draft” stage.
  4. Development of the LUZOD project (local data collection and processing equipment).
  5. Preparation of technical specifications for the manufacturer for production of transformer substation 10/04 kV.
  6. Coordination with the distribution system operator of project documentation.
  7. Organization of the execution of work and coordination of the actions of the general contractor and all related organizations for the laying of a 10 kV cable line.
  8. Acceptance and quality control of the manufactured transformer substation.
  9. Execution of construction and installation works of transformer substation.
  10. Carrying out testing and commissioning.
  11. Issuance of executive documentation.
  12. Organization, education and training of service personnel at the Customer’s site.
  13. Preparation of personal protective equipment for personnel.
  14. Preparation of an agreement for the distribution and metering of electricity with the distribution system operator.
  15. Organization of the departure of the metering service for the adjustment and sealing of metering devices.
  16. Preparation of documents for obtaining a Permit to operate the facility.
  17. Preparation of an agreement on the supply of electricity.
  18. Commissioning of the facility.

Specialists of Alteco company will always help you to find the best and most cost-effective way to power your facility, including modern renewable energy technologies and energy storage systems.