Task: To build a solar station for generating energy at a “green” tariff and save own consumption.
Solution: 138 polycrystalline solar modules JA Solar JAP60S01-275 with a capacity of 37.95 kW and a grid inverter Huawei SUN2000-33KTL-A (power 30 kW, online monitoring output) were installed.
Functions of the Alteco Group company: Design, delivery, partial installation, commissioning, warranty.
Result: A solar station with a capacity of 37.9 kW was put into operation. The payback period of the project is up to 5 years.
ground-mounted PV modules
Task: To build a solar station to generate energy at a “green” tariff and save own consumption
Solution: 138 polycrystalline solar modules JA Solar JAP60S01 (275 W) with a total power of 37.95 kW and a grid inverter Huawei SUN2000-33KTL-A (power 30 kW, 4 MPP trackers) are installed on the ground structure in 2 rows. The station is monitored remotely using the Smart Logger 1000 through the NetEco 1000S online platform.
Functions of the Alteco Group company: Design, delivery, partial installation, commissioning, warranty.
Result: A solar station with a capacity of 37.9 kW was put into operation. Due to the fact that the manufacture and installation of tables for PV modules was carried out by the Customer, it was possible to significantly save money for the installation of a solar station. Thanks to monitoring, it was possible to remotely adjust the parameters of the inverter to operate in a “bad” customer’s network. The payback period of the project is up to 5 years.
grid inverter 30 kW
view of the solar panel mounting structure