Task: To implement the project of a rooftop solar power plant for generating energy at a “green” tariff.
Solution:At first, 40 pcs of monocrystalline half-cell solar modules Risen-330W with a power of 13.2 kW and a network inverter Huawei SUN2000-20KTL-M0 (AC power 20 kW, 3 phases + online monitoring) were installed. Then another 20 pcs of JA Solar JAM60S10-340/MR mono half-cell module with a power of 6.8 kW were added.
Functions of the Alteco company: Design, supply, installation, commissioning, warranty.
Result: A solar station with a capacity of 20 kW was put into operation. The payback period of the project is up to 6 years.
Task: To implement the project of a rooftop solar power plant for generating energy at a “green” tariff.
Solution:At first, 40 pcs of monocrystalline half-cell solar modules Risen-330W with a power of 13.2 kW and a network inverter Huawei SUN2000-20KTL-M0 (AC power 20 kW, 3 phases + online monitoring) were installed. Then another 20 pcs of JA Solar JAM60S10-340/MR mono half-cell module with a power of 6.8 kW were added.
Functions of the Alteco company: Design, supply, installation, commissioning, warranty.
Result: A solar station with a capacity of 20 kW was put into operation. The payback period of the project is up to 6 years.
The panels on the roof and Huawei inverter
Roof mounting structure with raisedangle