On-grid solar station 20 kW, 2nd stage, tracker (Makarivskyi district, Kyiv region, Ukraine)

osykovo 0Task: To increase the capacity of the solar station from 10 kW to the design 20 kW. For more generation, use a solar tracking device.

Solution: A Catcher 40 tracking system (with the possibility of remote monitoring) and polycrystalline solar panels Yabang Solar YBP260-60 with a capacity of 10.4 kW were installed.

Functions of the Alteco Group company: Design, 3D-modeling, delivery, installation, commissioning, warranty.

Result: The 2nd stage of the solar station (10.4 kW) was put into operation. The payback period of the project is about 6-7 years.

osykovo 1osykovo 2

solar tracking system with control system and sensors

Task: To increase the capacity of the solar station to the design 20 kW. For more generation, use a solar tracking device.

Solution: A Catcher 40 tracking system (with the possibility of remote monitoring) and the 2nd stage of Yabang Solar YBP250-60 polycrystalline solar panels with a capacity of 10.4 kW were installed.

Functions of the Alteco Group company: Design, 3D-modeling, delivery, installation, commissioning, warranty.

Result: The second stage of the solar station (10.4 kW) was put into operation, which will generate a total of about 27,000 kWh of clean electricity per year and sell most of it at a “green” tariff of 5.85 UAH/kWh (as of 01.07.2016 – the tariff of 2015), which will allow you to receive income up to 158,000 UAH. The payback period of the project is 6-7 years.

osykovo 3 osykovo 4

3D visualization of the location of solar panels and the finished view of the station

osykovo 5osykovo 6

grid inverter 20 kW (3ph) with online monitoring output