On-grid solar station 34.3 kW (Novomoskovskyi district, Dnipropetrovsk region, Ukraine)

Task: To design a network solar station for generating energy at a “green” tariff, making the most of the roof area.

Solution: Installed 132 polycrystalline 260-watt solar modules with a capacity of 34.32 kW and a network inverter Huawei SUN 2000 – 33KTL (power 30 kW, 3 MPP trackers, the ability of online monitoring).

Functions of the Alteco Group company: Design, 3D-modeling, delivery, installation, commissioning, registration of a “green” tariff, warranty.

Result: A solar station with a capacity of 34.3 kW was put into operation. The payback period of the project is 5 years.

solar panels 1solar panels 2

exterior of a house with a “solar” roof

Task: To design a network solar station for generating energy at a “green” tariff, making the most of the roof area.

Solution: Installed 132 polycrystalline 260-watt solar modules with a capacity of 34.32 kW and a network inverter Huawei SUN 2000 – 33KTL (power 30 kW, 3 MPP trackers, the ability of online monitoring).

Functions of the Alteco Group company: Calculation of the station’s performance, 3D-modeling of the location of solar panels, calculation of shading of photo modules, supply of equipment and fasteners, commissioning of the station, warranty.

Result: The carried out work on 3D-modeling and design made it possible to maximally occupy the roof area with solar panels. Taking into account the peculiarities of the object, our specialists came to the conclusion that the solar station should be divided into 3 fields.Two fields (28.6 kW) are located on the slopes of the roof of the house and garage, the remaining field (5.72 kW) was placed along the fence.The used 30 kW inverter with 3 MPPT inputs made it possible to extract the maximum performance from the solar station. The calculation of the station generation and shading was carried out using special software.The result obtained fully justifies the expended efforts of Alteco’s specialists and meets the expectations of the Customer.A solar station with a capacity of 34.3 kW was put into operation. The payback period of the project is 5 years.

solar panels 3solar panels 4

solar panels on other roof slopes

solar panels fencesolar inverter

PV module design along the fence and grid inverter 30 kW

solar panels installation 1solar panels installation 2

installation of panels on the roof of the house

solar modelling 1solar modelling 2

solar modelling 3solar modelling 4

3D modeling of the location of solar modules

solar sheme 1solar sheme 2

switching circuits of solar station