Objective: Realization of a solar power plant project with PV capacity of 100-110 kW for electricity generation at a “green” tariff.
Solution: 3 grid-tied Huawei SUN2000-33KTL inverters (with remote monitoring capability) has installed and 396 polycrystalline solar panels JA Solar JAP6-60-270 with a total capacity of 106.9 kW has mounted.
Alteco Group functions: Design, supply, installation, “green” tariff connection, guarantee.
Result: The solar power plant had put into operation. Registration of “Green” tariff had performed. Payback period of the solar project is 5.5 years.
solar plant appearance 3D-modeling of PV modules’ arrangement
Objective: Realization of a solar power plant project with PV capacity of 100-110 kW for electricity generation at a “green” tariff.
Solution: 3 grid-tied Huawei SUN2000-33KTL inverters (with remote monitoring capability) has installed and 396 polycrystalline solar panels JA Solar JAP6-60-270 with a total capacity of 106.9 kW has mounted.
Alteco Group functions: Design, supply, installation, “green” tariff connection, guarantee.
Result: The solar power plant 106.9 kW had put into operation and the “green” tariff had registered. The technical and economic characteristics of this solar project allow generating about 107,000 kWh per year of “clean” electricity and receiving a revenue by “green” tariff of about $17,000 per year. Payback period of the project is 5.5 years.
mounting of PV modules
3×30 kW grid-tied inverters (3-phase) and monitoring device
solar plant’s monitoring in the NetEco system