Objective: Implementation of a ground-based solar power plant project in two stages to generate energy at a “green” tariff.
Project status: Two stages of solar power plant (600 kW + 600 kW) has put into operation.
Objective: Implementation of a ground-based solar power plant project in two stages 2×600 kW to generate energy at a “green” tariff.
Project status: Two stages of a solar power plant (600 kW + 600 kW) has put into operation.


design, development of detailed plan of the territory



solar power plant energy yield calculation


mounting of the solar structures


PV modules installation




installed rows with PV modules and ITS


the 1-st stage 600 kW has commissioned


the 2-nd stage 600 kW has commissioned

Solar power plant 1.2 MW (2 start-up complexes of 600 kW each)