Task: Based on the existing space and finances of the Customer, to install a network solar station for the sale of generated electricity at a “green” tariff. The project will be implemented in two stages.
Solution: A three-phase network inverter Fronius Symo 15.0-3-M with a power of 15 kW (with the possibility of remote monitoring) and polycrystalline solar panels JA Solar JAP6 270W/24V with a total power of 9.72 kW (1st stage) were installed.
Functions of the Alteco Group company: Design, supply, installation, consultations in the design of a “green” tariff, guarantee.
Result: The 1st stage of the solar station (9.72 kW) was put into operation. The payback period of the project is 6-7 years.
Task: Based on the existing space and finances of the Customer, to implement a grid solar station for the sale of generated electricity to the general grid at a “green” tariff, with the possibility of a phased increase in solar panels capacity up to 15 kW.
Solution: A three-phase grid inverter Fronius Symo 15.0-3-M (power 15 kW) and the 1st stage of polycrystalline solar panels JA Solar JAP6 270W/24V (power 9.72 kW) were installed. The inverter has the ability to connect to the Internet for constant On-line monitoring and “removing” reports.
Functions of the Alteco Group company: Design, supply, installation, consultations in the design of a “green” tariff, guarantee.
Result: The 1st stage of the solar station (power 9.72 kW) was put into operation, which will generate about 11,000 kWh of clean electricity per year, and sell most of it at a “green” tariff of 5.6 UAH/kWh (as of December 29, 2016). With the introduction of the remaining power of 5.28 kW, the station’s output will reach up to 17,000 kWh per year, which will make it possible to receive income of up to 77,000 UAH per year. The payback period of the project is 6-7 years.