On-grid solar station 15.2 kW (Kirovograd region, Ukraine)

aleksandriya main

Task: Implement a grid solar station for the sale of generated electricity to the general grid at a “green” tariff.

Solution: A network inverter Fronius SYMO 15.0-3-M (remote monitoring capability) and polycrystalline solar panels ABi-Solar CL-P60250 with a capacity of 10 kW (first stage) were installed, later the power of PV modules was increased to 15.2 kW (second stage).

Функции компании Альтэко Груп: Проектирование, поставка, монтаж, консультации в подключении “зеленого” тарифа, гарантия.

Functions of the Alteco Group company: Design, supply, installation, consultations in connection of the “green” tariff, guarantee.

Result: The 1st stage (10 kW) and the 2nd stage (5.2 kW) of the solar station were put into operation. The payback period of the project is 6-7 years.

aleksandriya top 1aleksandriya top 2

Task: Implement a network solar station for the sale of generated electricity to the general power grid at a “green” tariff, with the possibility of a phased increase in the capacity of solar panels up to 15.2 kW.

Solution: The network inverter Fronius SYMO 15.0-3-M, the 1st stage of polycrystalline solar panels Abi-Solar CL-P60250 with a capacity of 10 kW, was installed. Later, the 2nd stage of 5.2 kW solar modules was put into operation. The inverter has the ability to connect to a PC and the Internet for continuous On-line monitoring and reporting.

Functions of the Alteco Group company: Design, supply, installation, consultations in connection of the “green” tariff, guarantee.

Result: The 1st stage of the solar station (10 kW) was put into operation, which will generate about 11,000 kWh of clean electricity per year and sell most of it at a “green” tariff of 4.89 UAH/kWh (as of 12/29/2015). After the commissioning of the remaining power of 5.2 kW (2nd stage), the station’s output will reach about 16,500 kWh per year, which will make it possible to receive income of up to 80,000 UAH. The payback period of the project is 6-7 years. For online monitoring of the system – the network inverter is connected to the Internet via Wi-Fi.

setevaya solnechnaya stanciya 15 kvt kirovogradskaya oblast installation 1setevaya solnechnaya stanciya 15 kvt kirovogradskaya oblast installation 2

module mounting structure

setevaya solnechnaya stanciya 15 kvt kirovogradskaya oblast installation 3setevaya solnechnaya stanciya 15 kvt kirovogradskaya oblast installation 4

module mounting structure

aleksandriya installationsetevaya solnechnaya stanciya 15 kvt kirovogradskaya oblast installation 6

module mounting structure

setevaya solnechnaya stanciya 15 kvt kirovogradskaya oblast installation 8 setevaya solnechnaya stanciya 15 kvt kirovogradskaya oblast installation 7

network inverter 15 kW (3ph)